A procurement team releases a PO for six 2.5 MW standby gensets against a construction schedule that assumes 30-week delivery. The OEM's confirmation arrives quoting week 74, with an uncapped escalation clause and allocation language nobody saw in 2019. The building will be finished, fitted, and dark for almost a year.That sequence is now the default experience for data center backup power proc...